Administration Building & Transportation Center

admin

ARGYLE ISD ADMINISTRATION BUILDING

Due to student enrollment growth, capacity is needed at Argyle Intermediate School, which is adjacent to the Argyle ISD Administration building. The administration building will be repurposed for additional classroom space and the administration staff will move to the new facility in Canyon Falls.

Scope of Work

Construction: February 2021-December 2021
Opens: Projected March 2022
Serves: Argyle ISD administrative staff

TRANSPORTATION CENTER
Current transportation facility space is insufficient to park the Argyle ISD bus and vehicle fleet. District growth will require additional bus maintenance bays.

Scope of Work

  • Architect: Huckabee
  • Construction: Tegrity Contractors
  • Location: Adjacent to the new Argyle High School on Canyon Falls Drive
  • Cost: $5,000,000
  • Architect: TBD
  • Construction: TBD
  • Location: TBD
  • Cost: $4,000,000