New Stadium at AHS - Canyon Falls
The Bond 2022 package includes a new stadium at the Argyle High School campus in Canyon Falls. The stadium will be located behind the AHS fieldhouse and the existing artificial turf field and track will be used for the stadium. The new stadium was a separate proposition (Prop B) in the voter-approved bond package.
Scope of Work
Tentative Project Schedule
Design: January 2023 - December 2023
Procurement: December 2023 - February 2024
Projected Construction: 2024 - 2025
Projected Opening: August 2025
- Architect: VLK
- Construction: Pogue
- Capacity: 7,500 (expandable to 9,000)
- Home seating capacity: approximately 5,000 seats (including approx. 1,500 seatbacks)
- Stadium located behind AHS & will use existing artificial turf for playing surface
- Home side will be located on the west side
- Includes video scoreboard, two-story pressbox