Elementary School #3


Based on demographic projections, Argyle ISD's maximum elementary school capacity will be exceeded in 2022-2023. The new Elementary School #3 will be located on District-owned property in the Canyon Falls master-planned community, northwest of the middle school at the corner of Denton Creek Blvd. and Prairie Ridge Rd.

Scope of Work
  • Architect: Corgan
  • Location: Denton Creek Blvd. and Prairie Ridge Rd.
  • Cost: $35,874,673

Tentative Project Schedule
Design: June 2020-December 2020
Procurement: November 2020-January 2021
Construction: January 2021-May 2022
School opens: August 2022
Grades served: Pre-K-5th Grade